DCD Approval for Fire Fighting Drawings in Al Quoz
This case study covers the quoted DCD approval for fire fighting drawings at a fire fighting equipment installation company in Al Quoz, Dubai. The AED 3,300 quotation from LML/QTN/1047 covers preparing the drawings as per Dubai Civil Defence regulation, obtaining design approval from DCD, and conducting the inspection that releases the completion certificate. Government fees are paid directly by the client and VAT is separate.

Project facts
- Authorities
- DCD
- Quoted fee
- AED 3,300
- Scope
- Drawings, approval & inspection
- Status
- Quotation issued
At a Glance
The core facts of this fire fighting dcd approval approval engagement at a glance.
| Attribute | Value |
|---|---|
| Project type | Fire fighting DCD approval |
| Location | Al Quoz |
| Authority | Dubai Civil Defence |
| Quoted fee | AED 3,300 |
| Status | Quote only |
| Source ref | LML/QTN/1047 |
The Challenge
The client is a fire fighting equipment installation company in Al Quoz that needs DCD approval for a fire fighting drawing set. The quotation's limiting conditions define where the fee stays final: the client supplies the existing drawings, documents and green files; exceptional approval requirements, a design revision or a failed inspection each carry an extra charge; and all government fees are paid directly by the client, with VAT separate. Confirming those inputs at the start is what protects the quoted AED 3,300 fee.
The Approval Timeline
Tap a step for detailsWhat We Did
The steps we followed to prepare and submit this approval — from drawing review to final submission.
Site visit and drawing review
Review the existing fire fighting drawings, documents and green files supplied by the client, and confirm what the Al Quoz premises need for DCD compliance.
Prepare drawings as per DCD regulation
Prepare the fire fighting drawing set so it meets Dubai Civil Defence regulation in a single submission.
Obtain design approval from DCD
Submit the drawing set and supporting documents to Dubai Civil Defence, and follow up until design approval is obtained.
Coordinate government fees
Confirm which government fees the client pays directly, keeping the quoted professional fee separate and predictable.
Conduct inspection with DCD
Arrange and attend the inspection with DCD inspectors, and resolve any findings so the inspection passes.
Release the completion certificate
Once the inspection passes, finalise the DCD documentation and release the completion certificate.
This project combined our 2D Drawings, Approval Management and Document Clearing services to deliver a single, tracked submission from drawings through final inspection.
Documents & Requirements
The documents prepared or collected for this Dubai Civil Defence submission, and who supplied each one.
| Document | Description | Provided by | |
|---|---|---|---|
| Trade licence | Client's valid trade licence. | Client | |
| Tenancy contract | Tenancy contract for the Al Quoz premises. | Client | |
| Existing drawings and green files | Existing fire fighting drawings, documents and green files required by DCD. | Client | |
| Government fees | All government fees are paid directly by the client per the quotation. | Client | |
| Fire fighting drawing set | Fire fighting drawings prepared as per DCD regulation. | Wasleen | |
| DCD applications | Design approval and inspection applications submitted to Dubai Civil Defence. | Wasleen |
Requirements change as authorities update their regulations. Confirm the current document list with us before submitting — this case reflects the documents required at the time of this engagement.
Planned vs Actual
How the quoted timeline compared with what actually happened on this engagement.
| Stage | Planned | Actual | Note |
|---|---|---|---|
| Quotation issued | — | 3 March 2026 | — |
| Site visit & drawings | Weeks 1–2 | — | Indicative — typical DCD timelines |
| Design approval (DCD) | Weeks 3–5 | — | Indicative — typical DCD timelines |
| Inspection | Week 6 | — | Indicative — typical DCD timelines |
| Completion certificate | Week 7 | — | Indicative — typical DCD timelines |
Results
What this engagement delivered — limited to what the source documents actually support.
AED 3,300
Quoted fee
Dubai Civil Defence
Approval authority
Drawings, approval & inspection
Scope
Need the same approval handled for you?
Get a free quote for your fire fighting dcd approval project — no obligation, no hidden fees.
Frequently Asked Questions
Common questions about Dubai Civil Defence approvals like this one.
It covers preparing the fire fighting drawings as per Dubai Civil Defence regulation, obtaining design approval from DCD, and conducting the inspection that releases the completion certificate.
Dubai Civil Defence (DCD), which reviews fire and life-safety requirements for the fire fighting equipment design in Dubai.
The client provides the existing drawings, documents and green files, and pays all government fees directly. Wasleen prepares the DCD drawing set and handles the applications.
Additional charges apply for exceptional approval requirements, a design revision or a failed inspection; VAT is separate, and government fees are paid by the client.
Payment is 50% in advance, 40% during work progress and 10% after completion, as stated in quotation LML/QTN/1047.
This case study reflects a quotation issued on 3 March 2026 for AED 3,300; the approval scope is engaged and the final approval is not yet claimed.
Related Case Studies
DDA & DCD Approval for a Business Center Fit-Out in Dubai
Dubai Internet City
View case studyDCD Approval for Fire Fighting Design Revision in Jebel Ali
Jebel Ali
View case studyRelated approvals
Explore the Dubai Municipality Civil Defense NOC requirements, Dubai Municipality Completion Certificate requirements, MEP (Mechanical, Electrical, Plumbing) Approval requirements in detail.
Ready to Get Started?
Contact us today for a free consultation. We'll guide you through every step of the approval process.