The DEWA NOC fee typically ranges from AED 100 to AED 500, depending on the type of clearance (connection or otherwise). This fee is separate from meter installation and security deposits. Always check DEWA's official tariff for the latest rates.
What Does a DEWA NOC Cost for a New Connection?
DEWA NOC cost ranges AED 100–500, plus connection fees. Get exact fees, timelines & documents. Consult Wasleen for a smooth approval. Get a fixed-fee quote.
By Wasleen Liminal Approval Consultants — Approval Consultants
Back to DEWA Connection NOCAt a glance
A DEWA NOC in Dubai typically costs between AED 100 and AED 500, depending on the type of clearance. The total connection cost includes additional fees for meter installation (AED 300–500) and a security deposit based on load. Approval usually takes 3–7 working days for the NOC, with connection works completed in 5–10 days.

DEWA NOC Cost Breakdown
The DEWA NOC fee is only one part of your total connection cost. While the NOC itself typically ranges from AED 100 to AED 500, you must also budget for meter installation and a security deposit. Below is a breakdown of the verified fees.
| Fee Component | Indicative Amount | Notes |
|---|---|---|
| DEWA NOC fee | AED 100–500 | For connection NOC or clearance NOC |
| New connection (electricity) | AED 100–300 + per-kVA charges | Based on load; meter installation extra |
| Meter installation | AED 300–500 | Per meter, per DEWA tariff |
| Security deposit (electricity) | Refundable, based on load | Calculated per kVA; returned at closure |
| Load enhancement fee | Varies with added load (kVA) | Assessed on engineering review |
These figures are indicative and subject to DEWA's official tariff schedule. For an exact quote, consult our DEWA connection NOC service.
Timeline for DEWA NOC and Connection
The entire process—from application to energisation—typically takes 10–20 working days. Here is the verified timeline:
| Stage | Duration |
|---|---|
| Application & document check | 1–2 working days |
| Engineering review / NOC | 3–7 working days |
| Connection works / meter installation | 5–10 working days after approval |
| Final energisation / activation | 1–3 working days after inspection |
Delays can occur if documents are incomplete. Ensure you have all required paperwork before applying.
Documents Required for a DEWA NOC
To avoid rejection, prepare these common documents as per DEWA requirements:
- Title deed or registered lease / tenancy (valid registration)
- Dubai Municipality building permit (for new connections / fit-outs)
- Electrical layout / single-line drawings (stamped by certified engineer)
- Passport / Emirates ID of applicant (authorised signatory)
- NOC from developer / community (where applicable)
Missing any of these can delay your application. Our team can help you prepare a complete submission.
How to Apply for a DEWA NOC
Follow these steps to apply for a DEWA NOC:
- Gather all required documents (see above).
- Submit your application via DEWA's official portal or through an authorised consultant.
- Pay the NOC fee (AED 100–500) and any applicable connection fees.
- Wait for the engineering review (3–7 working days).
- Once approved, schedule meter installation and final inspection.
Using a consultant like Wasleen can streamline the process and reduce errors. We handle the paperwork and follow-ups for you.
Get Expert Help with Your DEWA NOC
Navigating DEWA approvals can be complex, especially for commercial properties. Wasleen Approvals specialises in DEWA connection NOCs and can manage the entire process—from document preparation to final energisation. Contact us to get a fixed quote and avoid unexpected costs.
Our consultants ensure your application is complete and compliant, saving you time and money.
For more details, visit our DEWA connection NOC page or our DEWA approval page.
Related Dubai approvals
You may also need these related Dubai approvals:
Frequently Asked Questions
The engineering review for a DEWA NOC usually takes 3–7 working days. After approval, connection works and meter installation take 5–10 working days. The entire process, including final energisation, typically completes within 10–20 working days.
Yes, a DEWA NOC is required for new electricity connections. The total cost includes the NOC fee (AED 100–500), connection fees (AED 100–300 plus per-kVA), and meter installation (AED 300–500). You'll also need to pay a refundable security deposit based on load.
Common documents include a valid title deed or tenancy, Dubai Municipality building permit, stamped electrical drawings, passport/Emirates ID, and a developer NOC if applicable. Incomplete documentation is a common cause of delays.
Yes, the DEWA security deposit for electricity is refundable. It is calculated based on your load (per kVA) and returned when you close your account. The deposit amount is separate from the NOC and connection fees.