What Does a DEWA NOC Cost for a New Connection?

DEWA NOC cost ranges AED 100–500, plus connection fees. Get exact fees, timelines & documents. Consult Wasleen for a smooth approval. Get a fixed-fee quote.

By Wasleen Liminal Approval Consultants — Approval Consultants

Back to DEWA Connection NOC

At a glance

A DEWA NOC in Dubai typically costs between AED 100 and AED 500, depending on the type of clearance. The total connection cost includes additional fees for meter installation (AED 300–500) and a security deposit based on load. Approval usually takes 3–7 working days for the NOC, with connection works completed in 5–10 days.

DEWA electricity connection approval process for a new property in Dubai
DEWA approval and connection timeline in Dubai

DEWA NOC Cost Breakdown

The DEWA NOC fee is only one part of your total connection cost. While the NOC itself typically ranges from AED 100 to AED 500, you must also budget for meter installation and a security deposit. Below is a breakdown of the verified fees.

Fee ComponentIndicative AmountNotes
DEWA NOC feeAED 100–500For connection NOC or clearance NOC
New connection (electricity)AED 100–300 + per-kVA chargesBased on load; meter installation extra
Meter installationAED 300–500Per meter, per DEWA tariff
Security deposit (electricity)Refundable, based on loadCalculated per kVA; returned at closure
Load enhancement feeVaries with added load (kVA)Assessed on engineering review

These figures are indicative and subject to DEWA's official tariff schedule. For an exact quote, consult our DEWA connection NOC service.

Timeline for DEWA NOC and Connection

The entire process—from application to energisation—typically takes 10–20 working days. Here is the verified timeline:

StageDuration
Application & document check1–2 working days
Engineering review / NOC3–7 working days
Connection works / meter installation5–10 working days after approval
Final energisation / activation1–3 working days after inspection

Delays can occur if documents are incomplete. Ensure you have all required paperwork before applying.

Documents Required for a DEWA NOC

To avoid rejection, prepare these common documents as per DEWA requirements:

  • Title deed or registered lease / tenancy (valid registration)
  • Dubai Municipality building permit (for new connections / fit-outs)
  • Electrical layout / single-line drawings (stamped by certified engineer)
  • Passport / Emirates ID of applicant (authorised signatory)
  • NOC from developer / community (where applicable)

Missing any of these can delay your application. Our team can help you prepare a complete submission.

How to Apply for a DEWA NOC

Follow these steps to apply for a DEWA NOC:

  1. Gather all required documents (see above).
  2. Submit your application via DEWA's official portal or through an authorised consultant.
  3. Pay the NOC fee (AED 100–500) and any applicable connection fees.
  4. Wait for the engineering review (3–7 working days).
  5. Once approved, schedule meter installation and final inspection.

Using a consultant like Wasleen can streamline the process and reduce errors. We handle the paperwork and follow-ups for you.

Get Expert Help with Your DEWA NOC

Navigating DEWA approvals can be complex, especially for commercial properties. Wasleen Approvals specialises in DEWA connection NOCs and can manage the entire process—from document preparation to final energisation. Contact us to get a fixed quote and avoid unexpected costs.

Our consultants ensure your application is complete and compliant, saving you time and money.

For more details, visit our DEWA connection NOC page or our DEWA approval page.

Related Dubai approvals

You may also need these related Dubai approvals:

Frequently Asked Questions

Related pages

Explore related approvals and guides for complete requirements, documents, and timelines.