As-Built Drawing Approval is required to certify that the completed construction matches the approved design drawings. This approval is a mandatory step before obtaining the final completion certificate and handing over the project. Processing typically takes 3–7 business days. Wasleen Approvals provides end-to-end assistance for your as-built-drawing-approval application in Dubai.

Typical timeline: 3–7 business daysTypical cost: AED 500 – 2,000

Authority

DM / Developer

Timeline

3–7 business days

Purpose

Verify built vs. approved design

Requirement

Mandatory for completion

What is As-Built Drawing Approval?

As-Built Drawing Approval is the process of submitting CAD drawings that reflect the actual constructed condition of a building or facility. These drawings must accurately document all changes made during construction from the original approved design. Dubai Municipality and most developers require approved as-built drawings before issuing a completion certificate or allowing occupancy. The as-built drawings must show all modifications, deviations, and field changes with clear markups, and must comply with the same CAD standards as the original submission. This process is critical for facility management, future renovations, and property transactions.

Wasleen Approvals has 8+ years of specialized experience securing As-Built Drawing Approval (Dubai) for clients across Dubai, including Business Bay, Downtown Dubai, Dubai Marina, JLT, and Al Qusais. Our team of registered engineers and approval specialists understands the specific requirements of each Dubai authority and manages the complete approval lifecycle.

From initial document preparation through submission, query response, and final certificate delivery, we ensure a smooth and efficient as-built-drawing-approval process. Our pre-submission audit catches 90% of potential rejection issues before they reach the authority, saving you time and money.

For comprehensive drawing support, explore: 2D Drawing Submission, 3D Design Approval, CAD Certification, and As-Built Drawings. Browse all 52+ approval types or visit our expert guides.

Who Needs As-Built Drawing Approval?

As-Built Drawing Approval (Dubai) is required for the following individuals and organizations:

  • 1Contractors completing construction projects requiring final approval
  • 2Property owners applying for completion certificate
  • 3Facility management teams requiring accurate building documentation
  • 4Consultants updating record drawings after project completion
  • 5Property buyers requiring as-built documentation for due diligence

Documents & Requirements

Ensure you have the following documents ready before submitting your application. Missing documents are the #1 cause of delays.

DocumentRequired
As-built CAD drawings (.dwg) showing all field changesMandatory
Original approved drawing set for comparisonMandatory
Site inspection reports confirming changesMandatory
Material and finish schedule (as installed)Mandatory
Approved completion certificate applicationOptional
Photographic evidence of key changesOptional

Requirements may vary based on project scope and authority updates. Always confirm the current document list with the issuing authority or consult our team.

Step-by-Step Process

Here's exactly how we manage your approval from start to finish. Each step is handled by our experienced team.

  1. 1

    Field Verification

    Conduct site survey to document all actual conditions, measurements, and any deviations from approved drawings.

  2. 2

    Drawing Markup

    Mark up approved drawings with all changes noted during field verification — redline markups for additions, strikethroughs for deletions.

  3. 3

    CAD Update

    Update CAD files to reflect as-built conditions with accurate dimensions, annotations, and revision cloud markups.

  4. 4

    Consultant Review

    Have the original design consultant review and certify that as-built drawings accurately represent the constructed condition.

  5. 5

    Authority Submission

    Submit as-built drawings to Dubai Municipality or developer for final approval.

  6. 6

    Approval Issuance

    Receive as-built drawing approval enabling completion certificate application.

Timeline & Cost Breakdown

Estimated processing times and costs for each stage of the approval process. Actual timelines depend on document readiness and authority workload.

StageDurationCost (AED)
Field Verification1–3 business daysAED 500 – 1,000
CAD Markup & Update2–4 business daysAED 500 – 1,500
Consultant Review1–2 business daysVaries
Authority Review & Approval3–7 business daysAED 200 – 500

Timelines and costs are indicative and may vary based on project complexity, document readiness, and authority workload. Contact us for a personalized assessment.

Common Rejection Reasons & How to Avoid Them

Learn from the most frequent reasons approvals get rejected — and how we prevent them with our pre-submission audit process.

As-built drawings do not match actual site conditions

Conduct thorough field verification and ensure every deviation from approved drawings is documented in the as-built set.

Missing revision clouds or markup notations

Clearly indicate all changes with revision clouds, arrows, and numbered revision tags per CAD standards.

Incomplete documentation of hidden or concealed changes

Document structural, MEP, and other hidden changes with notes referencing inspection reports.

Consultant certification missing or incomplete

Ensure original design consultant reviews and stamps the as-built drawings before submission.

Real Project Example

A real project we handled — demonstrating our experience and problem-solving capabilities.

Residential Villa in Al Barari

Authority

Dubai Municipality + Al Barari Developer

Timeline

10 days (complete process)

Challenge

The villa had 23 undocumented field changes from the approved design, including structural modifications and MEP rerouting. Original approved drawings were outdated.

Outcome

Comprehensive field survey conducted, all changes documented in as-built CAD, and approval obtained in 10 days enabling final completion certificate.

Why Choose Wasleen Approvals

We have successfully managed hundreds of Dubai Municipality / Developer approval applications. Here's what sets us apart.

Comprehensive field verification by experienced surveyors

Full CAD as-built drawing preparation in compliance with DM standards

Coordination with original design consultants for certification

Streamlined submission through DM and developer portals

Proven track record of first-attempt as-built approval

Frequently Asked Questions About As-Built Drawing Approval

Find quick answers to the most common questions about this approval process.

Related Approvals

Explore other approvals that may be relevant to your project.

Related Guides

Explore our comprehensive guides and Q&A pages for more detailed information.

Ready to Get Started?

Contact us today for a free consultation. We'll guide you through every step of the approval process.