Contractors must rectify defects in their work, maintain a valid DM license and classification, provide required documentation, and cooperate with DM inspections. They must also ensure their work complies with the Law's quality standards for buildings completed at least 20 years ago.
Contractor Responsibilities Under Law 3 of 2026 Dubai
Discover contractor responsibilities under Law 3 of 2026 Dubai. Learn defect rectification, DM licensing, and fines up to AED 1,000,000. Get expert guidance.
By Jamsheed Khalid — Senior Fit-Out Consultant
Back to Dubai Building Quality and Safety Certificate (Law No. 3 of 2026)At a glance
Under Law No. (3) of 2026 on Quality and Safety of Buildings in Dubai, contractors are responsible for rectifying defects in their work, maintaining DM licensing, and complying with the law's quality standards. They must cooperate with building audits and can face fines ranging from AED 100 to AED 1,000,000 per violation. The law applies to buildings completed at least 20 years ago, with compliance required within one year of the effective date.

What Law 3 of 2026 Means for Contractors in Dubai
Law No. (3) of 2026 on Quality and Safety of Buildings (the 'Law') introduces sweeping changes for construction professionals in Dubai. For contractors, the Law imposes explicit obligations regarding the quality of work, defect rectification, and cooperation with Dubai Municipality (DM) audits. This page outlines your key responsibilities under the Law, the associated penalties, and how Wasleen Approvals can help you navigate compliance.
The Law applies to all buildings in Dubai that received a Completion Certificate at least 20 years ago. Contractors involved in the original construction or subsequent renovation of such buildings must ensure their work meets the Law's standards. Non-compliance can result in fines from AED 100 to AED 1,000,000 per violation, with repeat violations within 2 years doubling the fine up to AED 2,000,000.
For help obtaining your certificate, Wasleen Approvals manages the full Dubai Building Quality Safety Certificate process — from Technical Report preparation to submission and follow-up until approval.
Key Contractor Obligations Under Law 3 of 2026
Contractors must actively participate in the Quality and Safety Certificate process. Your primary duties include:
- Rectifying any defects identified in the Technical Report within the specified timelines.
- Maintaining a valid DM license and appropriate classification for the building's height category.
- Providing all necessary documentation, including laboratory test results from EIAC-accredited labs.
- Cooperating with DM inspectors and providing access to work sites and records.
- Ensuring that all work complies with approved plans and the Law's quality standards.
| Obligation | Details |
|---|---|
| Defect Rectification | Contractors must fix defects found in the Technical Report within the timeframe set by DM. |
| DM Licensing | Must hold a valid DM license and classification matching the building's height. |
| Documentation | Provide lab test results, engineering reports, and other required documents. |
| Cooperation | Allow DM inspections and provide access to records and premises. |
| Quality Standards | Ensure all work meets the Law's quality and safety requirements. |
For more detail, see our guide on Engineering Office Responsibilities Under Law 3 of 2026 Dubai.
Defect Rectification: Your Responsibility as a Contractor
One of the most critical contractor responsibilities under Law 3 of 2026 is defect rectification. If the Technical Report identifies defects in your work, you are obligated to correct them. The Law requires that defects be rectified within a reasonable period, and failure to do so can lead to penalties.
The rectification process typically involves:
- Reviewing the Technical Report and identifying the defects attributed to your work.
- Submitting a rectification plan to DM for approval.
- Completing the rectification work within the approved timeline.
- Obtaining a follow-up inspection to confirm compliance.
Contractors who fail to rectify defects may face fines up to AED 1,000,000 per violation, and repeat violations within 2 years can double the fine to AED 2,000,000.
For more detail, see our guide on Building Management Obligations Under Law 3 of 2026 Dubai.
Penalties for Non-Compliance
The Law sets a fine range of AED 100 to AED 1,000,000 for any violation. The exact amount depends on the type and severity of the violation, as determined by the Executive Council Chairman resolution. Repeat violations within 2 years double the fine, up to a maximum of AED 2,000,000.
Only two amounts are fixed by the Law itself: the outer fine range of AED 100 to AED 1,000,000 for any violation, and the repeat rule — a repeat violation within 2 years doubles the fine, capped at AED 2,000,000. The exact amount for each individual violation type is not set in the Law; it will be determined by a follow-up Executive Council Chairman resolution.
Note: The per-violation fine schedule is not yet published. For the most accurate information, always refer to the Dubai Legislation Portal.
For more detail, see our guide on Building Inspection Process Under Law 3 of 2026 in Dubai.
How to Ensure Compliance with Law 3 of 2026
To avoid penalties, contractors should proactively align with the Law's requirements. Here are practical steps:
- Verify your DM license and classification are up to date and match the building height.
- Maintain detailed records of all construction work, including materials and test results.
- Respond promptly to any DM notices or requests for information.
- Engage a DM-registered engineering firm to prepare Technical Reports if required.
- Seek professional guidance from consultants like Wasleen Approvals to navigate the compliance process.

Get Expert Help with Law 3 of 2026 Compliance
Navigating the obligations under Law 3 of 2026 can be complex. Wasleen Approvals specializes in Dubai Municipality approvals and compliance. We can help you understand your responsibilities, prepare the necessary documentation, and avoid costly fines. Contact us today to ensure your projects meet the highest standards of quality and safety.
For more details on the Quality and Safety Certificate for buildings, including the application process and required documents, visit our dedicated page: dubai-building-quality-safety-certificate.
Related Dubai approvals
You may also need these related Dubai approvals:
Frequently Asked Questions
Fines range from AED 100 to AED 1,000,000 per violation, depending on severity. Repeat violations within 2 years double the fine, up to a maximum of AED 2,000,000. Exact amounts are set by the Executive Council Chairman resolution.
The Law does not specify a fixed period; the timeline is determined by Dubai Municipality based on the defect's nature. Contractors must submit a rectification plan and complete the work within the approved timeframe.
No, it applies to buildings that received a Completion Certificate at least 20 years ago. Contractors involved in such buildings must comply with the Law's requirements.
Yes, the Law provides a grievance mechanism. You can file an appeal within 30 days of the decision. It is advisable to seek professional assistance to prepare your appeal.
Related pages
Explore related approvals and guides for complete requirements, documents, and timelines.
Dubai Building Quality and Safety Certificate (Law No. 3 of 2026)
Full approval requirements, documents, and timeline
Engineering Office Responsibilities Under Law 3 of 2026 Dubai
Related guide
Building Management Obligations Under Law 3 of 2026 Dubai
Related guide
Building Inspection Process Under Law 3 of 2026 in Dubai
Related guide
Dubai Law No 3 of 2026 Complete Guide — Building Quality & Safety
Related guide